ELEVATE CONSTRUCTION UPDATES
HOME – ELEVATE CONSTRUCTION UPDATES
CONSTRUCTION Updates
Construction continues to advance at Elevate by Prescott in Arjan. We are pleased to provide our customers with the latest updates. Alongside the project progress images previously shared, we are also sharing the official progress report from the Dubai Land Department (DLD), including the date of the site inspection. As construction moves forward, we will continue to update all of our customers with further details and reports.
Activities Milestone
- 1st Floor: Firefighting and duct fitting work are currently in progress.
- 2nd Floor: LPG pressure testing is underway.
- 3rd Floor: Plaster work is being carried out.
- 4th Floor: Electrical wiring installation is ongoing.
- 5th Floor: Plumbing work is in progress.
- 6th Floor: Wall sawing work is currently being conducted.
- 7th Floor: Block work is actively ongoing.
- 8th Floor: Block work continues to progress.
- 9th Floor: Maintenance work is in progress.
- 10th Floor: De-shuttering work is being carried out.
- 11th Floor: Steel fixing is ongoing.
- 12th Floor: Slab casting work is in progress.